Read storyJointline were instructed to replace 104no, 4m x 4m concrete slabs at RAF Coningsby. The works consisted of the breaking out and removal of the existing concrete pads, then recasting the new concrete surface to site specification, including adjustment of ironwork and earthing pits to facilitate.
Expansion joints were then installed using fuel resistant material, along with the refreshing of the line marking.
The total area was in excess of 530m3.
All works were completed in normal working hours, working around the RAF Flying schedule.
In a significant stride towards enhancing road traffic safety and operational excellence, Jointline proudly announces its achievement of the ISO…
Read storyWe are thrilled to announce the completion of a line marking project at the Wilson-Thomson Helipad at Mull and Iona…
Read storyJointline is pleased to announce the strategic appointment of Anthony Roberts, CMgr FCMI, as Head of Highways Operations. Anthony brings…
Read story